Sprint 3 Planning Report

Table of Contents

Introduction

We need to finish the project in this project and review and test it.

All the team members have to check and test the project individually and comment on the implementation of other members. After that, we will change and improve the implementation , if needed.

Product Backlog

The following picture is a part of product backlog. Full product backlog is accessbile through [this link] Product Backlog

Sprint Backlog

Sprint Backlog

Sprint Goal

Clearly, goal of this project is to meet all the project requirements and review the code and test the project with various testcases. The remaining features that should be implement in this sprint is to upload, share and download files and also some limitations on file upload, like all the files in a particular library to be the same.

Definition of Done

Definition of done is specified in every Jira stories.

Acceptance Criteria

Acceptance criteria is specified in every Jira stories.

Estimation

Estimation is specified in every Jira stories.

Velocity

The total work in the sprint is 18 hours. So, the velocity is approximately 2.6 hours per day.