Move licence-changes to endpoint and split work #1600

Merged
merged 18 commits into from
Jan 7, 2025

Conversation

Cruikshanks
Copy link
Member

https://eaflood.atlassian.net/browse/WATER-4546

Part of the work to migrate management of return versions to WRLS from NALD

During the import from NALD, if a licence end date is changed, for example, if it has been revoked in NALD, our return version functionality needs to know about it. This is so we can reissue the return logs for the licence to match the changed end date.

We are actively trying to move away from the legacy code base, so this work was always going to be done in here. Initially, it would be triggered by our own import process, which was due to replace the legacy one. But that was when we thought ReSP would be taking over from NALD.

Now, the plan is for WRLS to encompass the final abstraction leg and take over from NALD. There is little point in replacing a complex import we intend to switch off in the next year.

But, knowing we'd need something in the interim, we created the /jobs/licence-changes job. The intent was to schedule this after the first NALD import job had completed (the one that downloads and extracts the NALD data) but before the main licence import
job
. That way, our job could compare the NALD and WRLS licence records to determine if an end date has changed.

But then we had our 'doh!' moment.

Our reissue return logs engine expects to be given a licence ID and the date the change applies. However, the WRLS licence record needs to have been updated for it to determine the start and end dates of the new return logs.

If we schedule /jobs/licence-changes before the licence import job, it will see the change but won't reissue anything because the WRLS record won't have been updated. If we schedule it after, it won't see any difference and won't trigger the reissue.

Doh!

So, we've needed to change tact on this completely. Now, we intend to

This change handles the refactoring and creation of the endpoints, plus the addition of a new model for the new table.

https://eaflood.atlassian.net/browse/WATER-4546

> Part of the work to migrate management of return versions to WRLS from NALD

During the import from NALD, if a licence end date is changed, for example, if it has been revoked in NALD, our return version functionality needs to know about it. This is so we can reissue the return logs for the licence to match the changed end date.

We are actively trying to move away from the legacy code base, so this work was always going to be done in here. Initially, it would be triggered by our [own import process](https://eaflood.atlassian.net/browse/WATER-4535), which was due to replace the legacy one. But that was when we thought ReSP would be taking over from NALD.

Now, the plan is for WRLS to encompass the final abstraction leg and take over from NALD. There is little point in replacing a complex import we intend to switch off in the next year.

But, knowing we'd need something in the interim, we created the [/jobs/licence-changes job](#1593). The intent was to schedule this after the first [NALD import job](https://github.com/DEFRA/water-abstraction-team/blob/main/jobs/import.md#nald-import) had completed (the one that downloads and extracts the NALD data) but before the main [licence import
  job](https://github.com/DEFRA/water-abstraction-team/blob/main/jobs/import.md#licence-import). That way, our job could compare the NALD and WRLS licence records to determine if an end date has changed.

But then we had our 'doh!' moment.

Our reissue return logs engine expects to be given a licence ID and the date the change applies. However, the WRLS licence record needs to have been updated for it to determine the start and end dates of the new return logs.

If we schedule `/jobs/licence-changes` before the licence import job, it will see the change but won't reissue anything because the WRLS record won't have been updated. If we schedule it after, it won't see any difference and won't trigger the reissue.

Doh!

So, we've needed to change tact on this completely. Now, we intend to

- _trigger_ `/licences/end-dates/check` from the [NALD import job](https://github.com/DEFRA/water-abstraction-team/blob/main/jobs/import.md#nald-import) rather than schedule it
- refactor `/jobs/licence-changes` as `/licences/end-dates`, but instead of processing changed licences it [stores the details of the change in a table](DEFRA/water-abstraction-service#2666)
- add a new `/licences/end-dates/process` endpoint that processes these 'licence change' records, and which will be triggered from the [licence import job](https://github.com/DEFRA/water-abstraction-team/blob/main/jobs/import.md#licence-import)

This change handles the refactoring and creating of the endpoints, plus addition of a new model for for the new table.
@Cruikshanks Cruikshanks added the housekeeping Refactoring, tidying up or other work which supports the project label Jan 6, 2025
@Cruikshanks Cruikshanks self-assigned this Jan 6, 2025
@Cruikshanks Cruikshanks force-pushed the update-licence-changes-to-store-changes branch from 7fd71a2 to a4a0d82 Compare January 7, 2025 08:45
@Cruikshanks Cruikshanks force-pushed the update-licence-changes-to-store-changes branch from a4a0d82 to a474f3d Compare January 7, 2025 10:39
Not sure why we were selecting from `NALD_ABS_LIC_VERSIONS` and then joining to `NALD_ABS_LICENCES` but as the service is called `FetchLicencesService`, and all the data is coming from `NALD_ABS_LICENCES` it makes sense to refactor the query to treat it as the main table to select from.

Now it reads as expected, select all licences with a 'CURR' licence version.
Our constraint causes the original version of the test to fail.
@Cruikshanks Cruikshanks marked this pull request as ready for review January 7, 2025 13:33
@Cruikshanks Cruikshanks merged commit 9018907 into main Jan 7, 2025
6 of 7 checks passed
@Cruikshanks Cruikshanks deleted the update-licence-changes-to-store-changes branch January 7, 2025 13:33
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
housekeeping Refactoring, tidying up or other work which supports the project
Projects
None yet
Development

Successfully merging this pull request may close these issues.

1 participant