Waku 2024 H2 Roadmap update #117

Merged
merged 15 commits into from
Sep 25, 2024
Merged

Waku 2024 H2 Roadmap update #117

merged 15 commits into from
Sep 25, 2024

Conversation

fryorcraken
Copy link
Contributor

No description provided.

Copy link

@jm-clius jm-clius left a comment

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Did a first pass and added some estimates/comments

content/waku/2024-gantt.md Outdated Show resolved Hide resolved
content/waku/2024-gantt.md Outdated Show resolved Hide resolved
content/waku/2024-gantt.md Show resolved Hide resolved
section Nim.darshankabariya
%% TODO: review estimate
Nwaku on Windows: nwaku-windows-n, 2024-08-15, 6w
section Js.weboko
Copy link

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Are rln v2 and API stabilization efforts for later?

Copy link
Contributor Author

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Good catch! Fixed. Can you please help provide estimate for all js-waku items.

Copy link

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Thanks for adding!

Won't we have API stabilization as a separate work stream? Though we discussed it - it is vaguely defined as we don't have any backlog for it. We can add it at the end of H2 as well so not to overcommit.

For estimates for dogfooding app I think 8w is good as it is aligned with beginning of Devcon.

For reliability all good as per waku-org/pm#186 (comment)

For rln v2 - I think 8w is good estimate but I am not sure as for the scope (in my mind it seems quite straightforward to do) so if possible I'd add 2w on top, if no we can go with current and extend if it is needed.

Copy link
Contributor Author

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Let's continue the planning discussion in discord

Copy link

@jm-clius jm-clius left a comment

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Added some more comments.

Public dogfooding web app: milestone, after pub-dogfood-web-app-1 pub-dogfood-web-app-2, 0
section Scale up number of Communities
Usage of rendezvous: milestone, after rendezvous-r, 0
section Demonstrate product market-fit
Copy link

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

One more thing that may belong here is finishing the Waku Whitepaper. This would roughly take the entire Q4 (12w) to finish, but be something that all Research engineers will work on in parallel to their other deliverables (a few hours each week).

Copy link
Contributor Author

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

added to roadmap: https://docs.google.com/document/d/1L8HvXtAYk-JqQL6w3RgCskXwegcTa0J5nyH9YL4LrQE/edit#heading=h.hejfvov7j7ux but as you say here, not much value to have it in Gantt chart.

Comment on lines 99 to 101
(simulation) Functionality and stress test store v3: sim-storev3, 2024-08-01, 8w
(simulation) relay reliability performance impact: sim-relay-rel, after sim-store-cmp sim-req-res, 4w
(simulation) req-res reliability performance impact: sim-reqres-rel, after sim-relay-rel, 6w
Copy link

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

This still seems mostly accurate except that we'll need a (significant) separate item for Store Sync. Reliability performance testing could also probably be more general.

I'd change it to:

 (simulation) Functionality and stress test store v3: sim-storev3, 2024-07-08, 8w
 (simulation) Functionality and stress test store v3: sim-storesync, 2024-09-01, 10w
 (simulation) Reliability performance impact: sim-rel, after sim-storesync, 10w

Comment on lines +25 to +34
%% Team legend:
%% task name: team (accountable person)
%% - r-*: research (jm-clius)
%% - t-*: telemetry (fryorcraken)
%% - n-*: nwaku (ivansete)
%% - j-*: js-waku (weboko)
%% - c-*: chat (plopezlpz)
%% - g-*: go-waku (fryorcraken)
%% - bd-*: BD (pedro)
%% - se-*: Solution Engineer (vpavlin)
Copy link
Contributor Author

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

For the next iteration I want the team leads to handle the Gantt Chart so set some names.

Which means everyone mentioned in this legend can check:

(1) In the Milestones overview with deliverables section, that every deliverable needed work from their team has a Gantt task with the right prefix after the keyword after. For example:

E2e reliability protocol Status integration: milestone, crit, after r-e2e-rel-status c-e2e-rel-status, 0
has work scheduled for research and chat team, but no work for js-waku and nwaku teams

(2) Then, ensure that the assignment of tasks to team members is roughly correct until 31 Dec 2024. What matters is the completion dates, as it is what is then committed to in roadmap.

@fryorcraken fryorcraken marked this pull request as ready for review September 25, 2024 04:16
@fryorcraken fryorcraken merged commit 987f2d2 into v4 Sep 25, 2024
@fryorcraken fryorcraken deleted the waku-gant-2024-H2 branch September 25, 2024 04:16
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
None yet
Projects
None yet
Development

Successfully merging this pull request may close these issues.

4 participants