FOSDEM 2020 video timeline

Mark Van den Borre edited this page Jan 20, 2020 · 7 revisions

December

  • brief network team:
    • where do the video network connections physically go?

Early January

  • print 6 copies of FOSDEM video manual
  • print location sheets for every camera

week before FOSDEM

Monday

  • rental gear inventory in digital form

Thursday 20200130

  • 16:00: Egbert & Sebastian drive rental gear van to penta hotel Brussels:
    • includes dinner stop @Sebastian's to avoid peak trafic
  • 21:00: .bg gang arrives back @penta hotel
  • 21:00-22:00: rental gear arrives @penta hotel
  • 22:00-23:00: .bg gang tags rental gear, stores it @penta hotel rooms

Friday 20200131

09:00

  • 09:00: .bg gang, Egbert, Sebastian load rental gear @penta hotel into .nl van:

  • 09:00-10:00: Jan, own video gear, Pieter arrive @ULB

  • 09:30: rental gear, .bg gang, Egbert, Julien, Luc, Mark arrive @ULB

  • tasks:

    • unload all a/v gear (to K1.105 if available, otherwise to corridor in front of VOC)
    • set up the physical voctop rack (in corridor if needed & move afterwards)
    • hang up video monitoring screen in VOC
    • install extra video monitoring screen in VOC
    • set up space under the auditorium: desk, chair, power extender, network, big monitor
    • stick placement sheet in every camera bag
    • help with other tasks until K1.105 available
  • K1.105 available?

    • move all a/v gear there
    • power extension cable from corridor
    • install small soho router with 4 video boxes (for testing cameras)
    • configure video cameras (see manual)
  • DC network available

    • install voctops onto vocto rack
  • ??:00 network at K1.105 available

12:00 campus officially open to us

  • per building video teams:
    • XLR cabling setup to video cam spots (coordinate with network)
    • set up tripods, video boxes & power extensions in rooms (unsupervised); coordinate with network!
    • empty flight case storage: 1 top floor of K, 1 in VOC, 1 AW under stairs, 1 upper H behind infodesk, 1 lower H under stairs
    • (until network available) help with other tasks
  • Vasil, Mark, 2 volunteers set up VOC:
    • test uplink to streaming servers
    • monitoring station

14:00

  • per building video teams:
    • install cams & mics in rooms
    • report back to VOC for testing
    • VOC does an end to end streaming test

Saturday

  • 08:30: per building teams:
    • full loop test per room
    • room status: streaming
  • 09:30: VOC starts recording onto SSDs
  • 10:15: streaming up everywhere, monitored by video volunteers inside the room, per building team and VOC
  • 19:10: cleanup
    • VOC remotely switches off video boxes
  • Install equipment in UB5132
  • Install equipment in UB5230

Sunday

  • 08:00: VOC remotely switches on video boxes
  • 08:45: (or devroom opening time -15 minutes): streaming up everywhere, monitored by video volunteers inside the room, per building team and VOC
  • 18:05: VOC remotely switches off video boxes
  • 18:05: teardown (per building video team):
    • fill flight cases (tick off check list per room!)
    • cameras to VOC cameras per building
  • 18:30: Egbert & Sebastian pack cameras into van, park @$safe_place, back to ULB (ETA: 20:00)
    • TODO Egbert & Sebastian: need safe place (or direct departure for .nl)

Monday

  • before 14:00: Egbert & Sebastian drive back a/v equipment to rental place