Notifications
You must be signed in to change notification settings - Fork 0
07.27.2020 TT Agenda
Nic edited this page Aug 3, 2020
·
1 revision
@nniicc @adam3smith @stahs @qqmyers
- Discuss PhP
Admin
- New repo for reporting and agendas
Seba & Jim Coordination
- PhP updates to Stage and Prod
Seba
- Selenium
- PhP
Jim
- Report |
-
- Time tracking for different projects
-
- It would be helpful to review the Hypothesis/EOLS meeting and potential action items/ties to other work: we talked about changes to Dataverse to support replacing files in a draft dataset, assigning/reserving file DOIs at creation time, and the potential for connecting the package structure for capturing data and annotations to the RDA BagIt/import mechanism. It would be useful to get a sense of which ones (if any) are things to start working on and when, how the work should be supported, etc.
Note - developer from UM dropped out - so we're going to need to find someone else to focus on front-end development. Joel can likely participate in UX testing, but may be more limited than we imagined.
Seba
Selenium design
- Destroying registered users is a design challenge
- Admin would have to login and then delete the session ... Seba doesn't want to take this approach...
PhP upgrade
- Stage verified except for composer being updated ...
- What is timeline for Prod ?
- Prod needs to be offline for short period - Seba will do this on the next weekend after SK's team is done testing...
How was PhP problem solved?
- Ubuntu aptitude packages have conflicts from dependence on LibCurl 3
- The control manifest of this file can be edited - Seba modified this so that it would be compliant with LibCurl and Shibboleth - and let us upgrade PhP ...
- While this solution hacky, but SEBA is confident :) that this is a stable solution ...
Jim + Seba
- short timeouts on dev and stage (Jira 1135)
- Drupal is timing out (seeing 502s) because of ... load balancer? This was solved on Prod but not on Stage and Dev
Jim
- Reporting broken down by project makes sense for all involved
- Hypothesis integration with Dataverse / ATI project for NSF LSS - there are two tickets in Jira now that describe preliminary work that JM can work on for the coming week
Priorities
- 2 ATI tickets
- Metrics work
- Drupal 9 in background (for now)
- Seba to adjust load balancer on Stage and Dev